B+T Group, FranceConstruction progress Chalampé

Following the start of site installation and ground preparation in November 2020, the building structures are now gradually being erected in slipform construction. The steel structures for the plant technology will be erected in July 2021. The organization of the commissioning, which will then take place from 2022, is also running at full speed.